What does a solar Owner's Engineer do?

The short answer. A solar Owner's Engineer checks the plant on the owner's behalf, against the design and the billing meter. The contractors still do the work, and the owner still approves every stage and every spend.

Why an owner needs one

A solar plant is run by several parties: the EPC contractor builds it, the O&M company runs it and the SCADA system reports on it. Each of them checks its own work, so no one is accountable for the whole. An Owner's Engineer reads the plant as a whole and holds each vendor to its obligations.

During construction

Much of a plant is buried within weeks of being laid: piles, earthing, cable joints and trenches. The Owner's Engineer checks the work before it is covered, energised or paid for:

A hold point is a stage the work cannot pass until its check has passed, for example earthing before backfill. More on oversight during construction.

In operation

The Owner's Engineer reviews generation against design, checks vendor obligations and payment claims, supports joint meter readings, works with manufacturers on warranty claims, and reviews proposed works before the owner approves them. A fault is closed only when the billing meter shows the recovery. More on oversight of a running plant.

What stays with the owner

The owner appoints the vendors and approves all spend. The Owner's Engineer reviews, supervises and recommends.

Independence

Renevik never acts as Owner's Engineer on a plant it built, owns or bid for, and that is written into every contract.