How long should a solar plant drawing set take?
The short answer. In our experience, a full solar plant drawing set takes 2 to 6 weeks. Renevik Engineering draws one in 5 working days from complete site inputs.
Why it matters
Every week a set waits is a week the build cannot start. The weeks go in chasing the consultant, sending the same inputs twice and waiting for each revision.
What a full set contains
For a 3.6 MW AC ground-mounted plant our set runs to 45 sheets:
- design: drawing list, strings and inverters, plant and site layout, DC and AC single line diagrams, cable schedule, earthing and lightning, structure and piles, bill of materials, protection and CEIG checklist;
- electrical: DC string and cable routing, AC routing, inverter and transformer yard, switchyard and HT panel, HT/LT schematic with relays and metering, auxiliary power, SCADA, CCTV and weather station;
- civil: grading and drainage, roads and fence, cable trenches, foundations, control room, mounting structure;
- studies: earthing, lightning risk, short circuit, relay coordination, lighting and fire layout;
- handover: safety labels, commissioning tests, inspection checklist, as-built list and the O&M handover pack.
A part set, with layouts and a single line diagram only, is not a full set.
What the engineer needs from the owner
The site boundary and contour survey, the soil investigation and earth resistivity, the module, inverter and transformer data sheets, the grid fault level at the connection point, and the load and connection route. A pile load test is needed before piles are approved. Until an input arrives, the sheet that needs it should say so and print the value as assumed.
Who signs it
Every sheet should stay FOR REVIEW · NOT FOR CONSTRUCTION until a licensed engineer stamps it.